The complete guide

Developing New Construction in Philadelphia: the complete guide

My guide to building for-sale homes in Philadelphia: finding land, zoning and variances, L&I permits, PWD stormwater, the tax abatement and impact tax, underwriting, and selling, from a local agent who works with developers.

Updated Written by Marco Di Gabriele, Partner at Rarity Real Estate Team, Keller Williams Empower

The short answer

Building a for-sale home in Philadelphia comes down to a handful of gates, and most of the risk is in the first two. Confirm the zoning in Atlas before you buy. If the plan is by right, L&I’s target for a one- or two-family new construction permit review is 15 business days. If it is not, you are headed to the Zoning Board, where the City’s own manual put the wait for a regular hearing at about 180 days as of March 2026. Budget the 1% Development Impact Tax, file for the 10-year abatement within 60 days of your building permit, and price the home off real comps on day one. Every figure below is dated and linked to where it came from.

I’m Marco Di Gabriele, a Partner at Rarity Real Estate Team at Keller Williams Empower. I’ve sold homes in Philly since 2017, and our team broke into new construction by finding land for developers and then selling what they built. I’ve also been through the variance process on my own project. This guide is everything I wish every builder knew before they bought their first lot here, in the order I actually use it.

Prefer to watch first? This is my step-by-step walkthrough of developing new construction in Philly. Rules and costs move, so use the dated figures on this page for the numbers.

Step-by-Step Guide: How to Develop New Construction in Philly Watch on YouTube.

The path from lot to sale

Here is the whole process on one screen. The clock column is what the City publishes for its own part of the work. Your architect, engineer, lender and contractor add their own time on top, so treat these as the minimum, not the plan.

City timelines checked November 22, 2026. Design, financing and construction time are not included.
StepWho you deal withThe official clock
1. Find and check a lotSeller, agent, Atlas, title companyNone. This is your due diligence.
2. Confirm zoningAtlas and the Zoning Summary GeneratorInstant lookup; confirm with your architect
3. Variance or special exception, if neededL&I refusal, RCO meeting, Zoning Board of AdjustmentFile within 30 days of the refusal; regular hearing wait about 180 days, accelerated about 140 days (March 2026)
4. Civic Design Review, if the project is large enoughPlanning Commission CDR CommitteeRequired above the size triggers below
5. Building permitL&I through eCLIPSE15 business days for one- or two-family new construction, 20 for most others, 5 if you pay for accelerated review
6. Abatement applicationOffice of Property AssessmentWithin 60 days of the building permit issue date
7. Build, inspect, Certificate of OccupancyL&I inspectorsCO comes with the building permit when the work passes
8. Launch and sellYour listing agentYour market sets this clock

Sources: Zoning Appeal Manual 2026.2, L&I Get a Building Permit, City abatement page, L&I Certificate of Occupancy.

Finding land

A lot of early investors buy a lot without putting much thought into it. They don’t really know the zoning, or whether the lot can hold what they want to build. A lot can look perfect and still be the wrong lot. Before you sign anything, confirm three things: the zoning district, the lot size, and that the person selling it actually owns it.

  • Match the lot to the product. If you want a single townhome, you usually want RSA-5. If you want multifamily, you might want RM-1. If you want mixed use, you’re usually looking at CMX. More on districts in the next section.
  • Make sure the lot can compete. Some listed land is too small to build a home that will actually compete with nearby new construction. In a June 2025 video I used an example of area new construction selling for $600,000 or $700,000. That was an example from that video, not a current price. The point stands: if the lot can’t support a product that fits the block, the purchase doesn’t work.
  • Look off market. The public sites are often picked over. A lot of the best land deals I see come through a good agent or a wholesaler, not Zillow or the MLS.
  • Start every address in Atlas. For any property in the city it shows the zoning, overlays, permits already pulled, open violations and the tax assessment.

A caution from a deal we almost did

We almost got scammed buying a parking lot. The person we were talking to when we went under contract was not the real seller. It was someone acting like the owner, with fake IDs and documents that made it look real. We found the actual owner, got in touch with him, and bought the lot from him. Verify ownership, use a real title company, and do the legal work. Don’t just fall in love with the dirt.

Philadelphia Land Bank

The Philadelphia Land Bank sells publicly owned surplus land. You start with an Expression of Interest, which is not an application, and the Land Bank says it will contact you within 30 days. Properties offered competitively are advertised for at least 30 days, and the policies call for an agreement no later than 120 days after the submission deadline. Dispositions also go to City Council before settlement, and deeds can carry restrictions on what you build and when. Read the Land Bank disposition policies before you plan a timeline around a Land Bank lot, because it is a slower and more conditional path than a private purchase.

Sheriff sales

The Sheriff’s Office runs its sales online through Bid4Assets. Under the current conditions of sale for mortgage foreclosures, you put a deposit down before the auction, owe 10% of the price by 5 PM the next business day, and owe the other 90% by the 15th calendar day after the auction. Properties are sold as is, with no warranties of any kind, so you generally can’t inspect inside first. Tax sales add another wrinkle: the Sheriff’s Office says the owner or other parties may be able to redeem the property after the sale, and that generally there are 9 months to redeem a non-vacant property from the date the Sheriff acknowledges the deed. Talk to a real estate attorney before you bid. Sources: Conditions of Sale for Mortgage Foreclosure and Conditions of Sale for Tax Sales.

Zoning: what you can build by right

If you’re going to develop in Philly, understanding the zoning code is pretty much everything. Zoning decides what you can build on a parcel. Get it wrong and the project doesn’t get approved. Don’t buy land because there’s a triplex next door and assume you can build one too. That property may be grandfathered, and your lot may only be zoned for a single-family home.

Philadelphia Zoning Basics that Beginners Need to Know (RSA-5, RM-1, CMX Explained) Watch on YouTube.

The districts I see most on for-sale projects

  • RSA-5 is the common single-family attached district. If you find a lot zoned RSA-5, you can most likely build a traditional attached townhome like the ones you see across most of the city. It’s the base-level residential zoning I start with.
  • RM-1 is a residential multifamily district, a different product than a single townhome.
  • CMX-1 and CMX-2 are neighborhood commercial mixed-use districts. CMX-1 is often a corner store lot. In the zoning video I explain why a CMX-1 lot next to an RM-1 building is worth a closer look, but have your architect confirm what the code allows on that specific lot.
  • CMX-3 and up, RM-2 and up are the higher-density districts where floor area bonuses come into play.

Underused zoning, and uses that are only grandfathered

One way to find opportunity is underused zoning, for example a lot zoned CMX-2 that holds a single-family home today. Planners rezone areas over time, so you’ll find properties with a higher designation than what’s built. You’ll also find the opposite: a building that’s grandfathered as a multi-unit but is now only zoned single-family. If you buy that thinking you can redevelop it as multifamily, you may not be able to, especially if it doesn’t have the right rental licenses. That’s why I start with the official district, not what the building looks like.

Tools to use first: Atlas for the district and overlays, then the Zoning Summary Generator for a plain summary of what the district allows. A good architect who knows Philly zoning should confirm it before you close.

The Mixed Income Housing Bonus

If you want more than the base zoning allows, the Mixed Income Housing Bonus is the City’s main tool. You either set aside 10% of the units as affordable or, in some cases, make a payment, and in return you earn more floor area, more units or more height. Here is what the 2026 fact sheet says:

From the Department of Planning and Development’s MIHB Fact Sheet 2026 (June 3, 2026). Use the City’s calculator for your lot; Planning Commission staff confirm the final numbers in zoning review.
Your districtWhat you can earnPayment option (instead of affordable units)
RM-1, CMX-1, CMX-2, CMX-2.525% more units at the moderate-income level, 50% more at low-income; a 7 ft height bonus in RM-1, CMX-1 and CMX-2 only if you build 3+ units and build the affordable units$13,600 per allowed unit (moderate) or $17,700 per allowed unit (low income)
RM-2 to RM-4, RMX-1 to RMX-3, IRMX, CMX-3 to CMX-5Extra floor area from 25% to 400% of lot area, depending on district and level$11.30 per sq ft of total allowed floor area (moderate) or $14.60 (low income)

Three details matter. The payment option is only open if you build 10 or more units, or if less than half the floor area is residential. Payments are based on what’s allowed, not what you build. And you submit the Acknowledgement Form with your zoning permit application, with the legal agreement and payment due before building permits. Sources: MIHB Fact Sheet 2026 and the City bonus calculator page.

Not sure what your lot allows?

Send me the address and what you want to build. I’ll look at the zoning with you and tell you honestly whether I think it pencils.

Variances, RCOs and the Zoning Board

If your project doesn’t fit the zoning, you need a variance, and getting one isn’t always easy. Here is how it works. You apply for a permit, L&I issues a refusal, you appeal to the Zoning Board of Adjustment (ZBA), you meet with the neighborhood’s Registered Community Organization (RCO), and then you present your case at a hearing that works like a courtroom.

How to Get a Variance Approved in Philly (The Right Way) Watch on YouTube.

The steps and the deadlines

  1. Appeal within 30 days of the Notice of Refusal or Referral. Filing online in eCLIPSE is fastest.
  2. Contact the Coordinating RCO within 20 days of the ZBA’s email naming it, and send notice to the other affected parties in the same window. The code requires notice to every property within 250 feet and on the same and opposite blockface.
  3. Hold the community meeting. The Coordinating RCO is supposed to make a good-faith effort to hold it within 45 days of your filing date. If the RCO doesn’t make a good-faith effort to meet, the Board will still hear your appeal as long as you gave notice, tried to contact the RCO, waited 45 days from filing, and did your posting and exhibits.
  4. Post the hearing poster on the property at least 21 days before the hearing.
  5. Submit exhibits at least 14 days before the hearing.
  6. Get your decision. The Notice of Decision usually arrives 2 to 3 weeks after the vote. Any party has 30 days from that notice to appeal to the Court of Common Pleas.
ZBA fees as of August 1, 2026, from the Zoning Appeal Manual 2026.2. Your exact fee is printed on your Notice of Refusal.
ZBA feeAmount
Existing one- or two-family dwellings$125
Affordable housing projects$125
All other properties$811
Accelerated hearing$995 per property (maximum $2,985)
Administrative review$265

How long it takes: the manual says that as of March 2026, the wait for a regular hearing was about 180 days, or about 140 days with the accelerated fee, with roughly 600 to 650 appeals in the queue. If you miss a step, the hearing is usually continued four to six months. Sources: Zoning Appeal Manual 2026.2 and Philadelphia Code 14-303(12).

What a hardship really means

A hardship usually can’t be financial. Wanting to turn a single-family lot into multifamily because it makes more money isn’t a hardship. A hardship is more like a lot that truly can’t be built the way the code describes, for example an unusually large lot zoned for one home. And RCOs are the voice of the neighborhood. Meet with them early, learn what matters to them, and shape a plan that makes a real case. Bring your architect and, when you need one, a zoning attorney.

What it took on my own project

I developed a six-unit apartment building with a partner on land zoned RSA-5, which allowed one single-family home. The parcel was large and the nearby properties were already multi-unit, so we felt a multi-unit was the better use. We went through it during COVID, with more delays than you’d probably see now. In one video I said it took the better part of 9 to 12 months, and in another I remembered it as over a year. We got shot down once or twice at the community meetings before we landed on a plan the neighborhood could support. That’s my experience, not an official timeline. Use the City’s current numbers above for planning.

Civic Design Review for larger projects

Big projects get an extra public design review. Civic Design Review is required for new construction that creates more than 100,000 square feet of new floor area or more than 100 new units. The trigger drops to more than 50,000 square feet or 50 units when the project affects a property in a residential district, which the code defines as sharing a lot line, sitting across an alley, or being nearby on the same or facing blockface. L&I won’t issue a final decision until CDR is done, and CDR projects also get the RCO meeting. Source: Philadelphia Code 14-304(5), Table 14-304-2.

Permits and L&I

Once zoning is clear, you’re in design and permitting. This is where you work closely with an architect who understands Philly zoning and L&I, so the set you submit isn’t outside what the code allows. If you can build by right, focus on a clean permit set and get shovels in the ground. This is also when you bring in a general contractor to price what you designed.

  • Review times. L&I lists 15 business days for new construction of a one- or two-family dwelling and 20 business days for most other projects, plus a business day for pre-processing. That’s L&I’s review clock, not the total time to a permit in hand. Corrections and resubmissions add time.
  • Accelerated review. New construction applications with plans can pay for accelerated review, which L&I reviews within 5 business days. The fee is $2,000: $350 when you apply and the rest once approved, and it doesn’t count toward your permit fee.
  • Certificate of Occupancy. New construction needs a CO. For new construction it comes with the building permit when the work is complete and passes final inspection, with no separate application or fee.
  • Permit data is public. Buyers and their agents can look up your permits and any violations in Atlas. Keep the file clean.

Sources: L&I Get a Building Permit and L&I Get a Certificate of Occupancy.

Mid-build, a finish can look off before the house is done. I’ve seen teams stick with a design that looked wrong at 50% and have it come together at the end. That only works if the designer and the builder are actually talking to each other.

Water, sewer and stormwater

The Philadelphia Water Department reviews stormwater based on how much ground you disturb. PWD updated its Stormwater Regulations on July 1, 2026, and one change is good news for townhome builders.

From PWD Development Services, checked November 22, 2026. Watershed and project type can change the requirements, so confirm with PWD.
Earth disturbanceWhat PWD requires
Under 5,000 sq ftNo ERSA submission. Install erosion and sediment controls as needed.
5,000 to under 15,000 sq ftERSA application with an Erosion and Sediment Control Plan, which now needs PWD approval.
15,000 sq ft to under 1 acreERSA application with a Conceptual Stormwater Management Plan, then a Post-Construction Stormwater Management Plan.
1 acre or moreAll of the above, plus an NPDES permit from PA DEP.

The townhome change: since July 1, 2026, PWD exempts Small Residential Development from post-construction stormwater management. That means a project disturbing less than one acre with buildings used only as one- or two-family homes. You still need the erosion and sediment plan if you disturb 5,000 square feet or more. In the Darby and Cobbs Creeks watershed, post-construction rules start at 5,000 square feet, and parts of the Wissahickon watershed can be lower. Sources: PWD Review and Permitting and PWD July 2026 newsletter. For new water and sewer service, start with PWD Development Services early in design, not after framing.

Taxes and fees on a new home

Development Impact Tax: 1%

Anyone who pulls a building permit for residential new construction over $15,000 pays the Development Impact Tax, 1% of construction cost. Half is due when the building permit is issued and half before the certificate of final inspection, and the City will hold your final if it isn’t paid. For new construction, eCLIPSE calculates the cost from a per-square-foot table, not from your contractor’s bid. Certain affordable housing projects certified by the Department of Planning and Development are exempt. Sources: Development Impact Tax and Philadelphia Code 19-4401 to 19-4403.

Selected rows from the Department of Revenue’s table of locally adjusted ICC costs that eCLIPSE uses for the tax. These are tax valuation figures, not what it will cost you to build.
Construction typeOne- and two-family, per sq ftMultiple family, per sq ft
VB$89.15$113.88
VA$94.75$118.57
IIIB$98.44$130.52
IIIA$102.12$135.04
IA$157.40$256.21

Example of the math only: a 2,400 square foot type VB single-family home would be valued at 2,400 x $89.15 = $213,960 for the tax, so the 1% tax would be about $2,140, split into two payments. Your eCLIPSE application sets the real number.

The 10-year tax abatement

The abatement is one of the biggest reasons buyers pay up for new construction here, so it’s part of your product. Under the current New Construction for Residential Properties program (Ordinance 1456-A), the land is always taxed, and the abated share of the building drops 10% a year over 10 years:

Declining abatement chart from the Office of Property Assessment application, revised February 2024. Year 1 is the first 12 months of the abatement, not a calendar year.
Year of the abatementShare of the building abatedShare of the building taxed
Year 1100%0%
Year 290%10%
Year 380%20%
Year 470%30%
Year 560%40%
Year 650%50%
Year 740%60%
Year 830%70%
Year 920%80%
Year 1010%90%
  • You apply, not your buyer. OPA’s instructions say the owner or developer building the home applies, within 60 days of the building permit issue date. OPA says you must file on time, so put this date in your schedule the day the permit issues.
  • When it starts. The first month after the title date or the first month after the CO, whichever is later. Once set, the dates don’t change.
  • Stay in good standing. You have to be current on what you owe the City, and after approval a signed owner’s certificate is needed to put the abatement in place.
  • Eligible homes. Single homes, duplexes, triplexes, townhouses, multifamily including condos, and mixed-use buildings at least 50% residential by assessable square footage. Not hotels.
  • The 30-month development abatement. Separately, State Act 175 offers a 30-month abatement during construction for new residential work. It starts the first day of the month after L&I issues the building permit, and you apply by December 31 of the year the permit is issued.

Sources: City abatement page and OPA application and instructions. To estimate taxes on a specific address, use my tax abatement lookup and calculator.

Philly's 10-year tax abatement: what you need to know (June 27, 2025) Watch on YouTube.

At the sale

Philadelphia’s realty transfer tax is 4.578% of the price (3.578% City plus 1% Commonwealth). It’s often split between buyer and seller, but that’s a negotiation, not a rule. In new construction, covering some of the buyer’s share is one of the levers I see builders use. The combined Real Estate Tax rate your buyer will pay on the taxable part is 1.3998%. Sources: Realty Transfer Tax and Tax Rate History.

Costs, financing and underwriting

People want a straight cost-per-foot answer, so here’s mine. In my experience, the hard cost to build a new home in Philly runs roughly $150 to $200+ per square foot, depending on finishes, size, site conditions, structure, parking and more. That’s construction only. It doesn’t include land, soft costs like design, permits and taxes, or financing, so your all-in cost per foot will be higher. Compare it with what new homes actually sold for: a median of about $281 per square foot over the last 12 months, in the sold price table below. The gap between those two numbers has to cover the land, the soft costs, the financing, the sale and your margin. Get a priced budget from your contractor for your actual plans, because your project can land outside this range. The ICC table above is what the City uses for a tax, not a bid. Here’s how I underwrite a deal.

  1. Start with the exit. What will the finished home sell for, based on recent closed new construction nearby, not the best sale on the street?
  2. Land and closing costs. Purchase price, your share of transfer tax, title, legal.
  3. Soft costs. Architect and engineer, survey, permits and the 1% Development Impact Tax, ZBA fees if you need a variance, MIHB payment if you use the bonus, insurance, and carrying costs while you wait on approvals.
  4. Hard costs. Your general contractor’s priced budget from the permit set, plus a contingency.
  5. Financing. Interest and points on the acquisition and construction loans for the full timeline, including the ZBA wait if you need one.
  6. Sales costs. Commissions, staging, photos, and any buyer incentives such as transfer tax help.
  7. Margin. What’s left has to justify the risk and the time. If it only works at the dream price, it doesn’t work.

Financing basics: most for-sale builders use an acquisition loan or cash for the land and a construction loan that draws as work is completed and inspected. Lenders will want your plans, budget, timeline, and proof of your experience and equity. Talk to two or three local construction lenders before you go hard on a lot, because their terms shape your margin as much as your bid does.

In August 2023 I recorded a screen-share of the underwriting sheet I use on larger developments, covering lot coverage, costs, sale ranges and target margins. The figures in it are a 2023 worked example, not current costs, so don’t copy them into a live pro forma. There’s also a download at marcodigabriele.com/dealanalyzer.

Underwriting Large New Construction Developments in Philly (August 2023). Figures in the video are a worked example, not current costs Watch on YouTube.

Where new homes are being permitted

Every neighborhood here has its own micro-market, so I don’t treat Philadelphia as one set of numbers. One public signal of where builders are active is L&I’s permit data. I pulled every Residential Building permit marked New Construction issued from November 1, 2025 through October 31, 2026. That’s 674 permits citywide, and these ZIP codes had the most:

Source: City of Philadelphia L&I Building and Zoning Permits open data, Residential Building permits with type of work New Construction, issued November 1, 2025 to October 31, 2026, queried November 22, 2026. Counts are permits, not homes; one permit can cover one home or a two-family building. Neighborhood names are a general guide, since ZIP lines don’t follow neighborhood lines.
ZIPNew construction permitsIncludes parts of
1913396Fairhill and West Kensington
1914680Graduate Hospital and Point Breeze
1912579Fishtown, East Kensington and part of Port Richmond
1912352Northern Liberties and Poplar
1914439Germantown
1912137Brewerytown, Sharswood and parts of North Philadelphia
1913434Port Richmond and Kensington
1914526Parts of South Philadelphia, including Packer Park and Girard Estate
1914026Hunting Park and Nicetown
1912223Olde Kensington, Ludlow and the blocks around Temple University

For larger buildings, the Commercial Building permits marked New Construction in the same period listed the most new units in 19122 (548 units), 19125 (415), 19104 (391), 19144 (385) and 19133 (308), based on the unit counts entered on the permits. Permit counts tell you where competition and labor demand are, not where a deal will work. Pair them with closed sales on the specific blocks. Source: L&I permits open data.

Here’s the other side: where new homes actually sold. These are the 10 ZIP codes with the most new construction sales on Bright MLS from November 1, 2025 through October 31, 2026, with the median resale price per square foot buyers paid. 19133 had the most permits but only 5 new construction sales on Bright MLS in the same period, so it isn’t on this list. Permits point to what’s coming. Sales show what has already closed.

Based on information from Bright MLS for the period November 1, 2025 through October 31, 2026. Information Deemed Reliable but Not Guaranteed. Prior-year figures are based on information from Bright MLS for the period November 1, 2024 through October 31, 2025. Information Deemed Reliable but Not Guaranteed. Sold price per above-grade finished square foot as entered on the listing, usually the builder’s estimate. Days on market can read 0 or 1 when a builder enters a home that’s already under contract, which is why 19131 shows 1. Sale to list is the sold price divided by the original list price.
ZIPIncludes parts ofSalesMedian sold $/sq ftPrior 12 months $/sq ftMedian days on marketSale to original list
19146Graduate Hospital and Point Breeze67$312$3863798.3%
19125Fishtown and East Kensington58$298$3033699.5%
19131Wynnefield and parts of West Philadelphia52$285$2721100.0%
19122Olde Kensington and Ludlow40$228$25950100.0%
19123Northern Liberties and Poplar37$336$3232699.4%
19148East Passyunk and South Philadelphia east of Broad32$243$2975298.0%
19134Port Richmond and Kensington23$225$18067100.0%
19147Queen Village, Bella Vista and Pennsport18$355$4415095.7%
19128Roxborough and Manayunk17$298$265106100.0%
19107Washington Square West and Midtown Village16$927$87534100.0%

For neighborhood context, see my new construction neighborhood guides. For the full monthly numbers by size, home type and area, including supply and how new homes compare with resale, see my Philadelphia new construction market report.

Designing, pricing and selling

You spent months, maybe years, getting the project built. Selling it is a different job. I work with developers from early design through pricing, and I’ve seen what keeps momentum and what quietly eats profit.

Selling New Construction in Philly for Maximum Profit / ROI Watch on YouTube.

Design for the end buyer

Layouts, finishes, price point and buyer expectations all get decided in design, long before the sign goes up. Talk to an agent who sells a lot of new construction about who is likely to buy and what they want. One example I’ve seen recently is demand for a real home office, so when we can, we build that space in. Decide early whether you’ll sell or hold as a rental, because a lot of design decisions push a project one way or the other, and after framing you’re mostly stuck with what you drew.

The two mistakes I see most are overbuilding and underbuilding. Overbuilding is finishes too high-end for the likely price, or a home bigger than buyers on that block want. Underbuilding is finishes that miss expectations or a layout that doesn’t work for the buyers shopping in that price range.

Comps and absorption

When I sell new construction I track showings and sales in that specific neighborhood, including the most recent pending and closed sales, and use that to see where a project stands. For the citywide picture, here’s what new homes sold for.

What new homes sold for

From November 1, 2025 through October 31, 2026, 481 new construction homes sold in Philadelphia County through Bright MLS at a median of $575,000 and $281 per above-grade square foot, down from $600,000 and $299 in the prior 12 months. The median home sold in 42 days, up from 38, at 99.3% of its original list price. One thing to be clear about: sold price per square foot is what buyers paid for a finished home, land included. It is not a build cost. For the build side, I use a rough hard cost of $150 to $200+ per square foot before land, soft costs and financing, as I explain in the costs section above. Use the sold numbers for the top line of a pro forma, not the cost side.

Based on information from Bright MLS for the period November 1, 2025 through October 31, 2026. Information Deemed Reliable but Not Guaranteed. Prior-year figures are based on information from Bright MLS for the period November 1, 2024 through October 31, 2025. Information Deemed Reliable but Not Guaranteed. Active listings are based on information from Bright MLS as of November 22, 2026. Information Deemed Reliable but Not Guaranteed. Square footage is above-grade finished area as entered on the listing, usually the builder’s estimate. Months of supply is active listings divided by the average monthly sales over the last 12 months. Twins and detached homes have few sales, so read those rows with care.
Home typeSalesMedian sold $/sq ftChange vs. prior 12 monthsMedian days on marketSale to original listActive median list $/sq ftMonths of supply
Townhouse or rowhome337$269-6%5099.1%$2797.2
Condo107$317-20%15100.0%$8535.8
Twin14$250+6%8093.0%$29713.7
Detached20$262-9%6696.6%$29112.0
All new construction481$281-6%4299.3%$2907.2

Supply is the number I’d watch. As of November 22, 2026, there were 290 active new construction listings, plus 6 coming soon and 72 under contract or pending. At about 40 sales a month, that’s roughly 7.2 months of supply. Active listings are asking a median $290 per square foot, a little above the $281 that sold, and the condo asking figure is pulled up because about half of the active condo listings are in Center City ZIPs 19102, 19103, 19106 and 19107, where many ask over $1 million. If you’re pricing a project, price it against what closed nearby, not what’s sitting.

Launch, staging and price

  • Launch when it’s ready. Unless you’re intentionally pre-selling, which is its own process, wait until the home is cleaned, punch-listed and photographed. Construction dust doesn’t show well.
  • Stage it. I suggest staging almost every new home we sell. Many Philly new builds are similar in layout and size, and staging is a real differentiator. Do it before the photo shoot. Virtual staging is an option if a full stage isn’t in the budget.
  • Price it right on day one. Come to market at the right number, not the dream number. Days on market make buyers ask what’s wrong. Buyers often search in $25,000 steps on the big portals, which is why I talk about adjusting in those steps if a launch needs a correction. That’s a search-behavior note from my May 2025 video, not a promise about a price.
  • Stay close. Punch-list items, showing feedback and a price that isn’t landing all get worse if nobody watches them week to week.

How I work with developers

Our team broke into new construction by sourcing land for developers, then selling the homes once they were built. That’s still how I like to work: in at the beginning, not just at the listing.

  • Land. I look for lots and small sites, often off market, that fit the product you build.
  • Feasibility. Send me an address and I’ll walk the zoning, the likely product, and the sale comps with you before you commit.
  • Design input. I’ll tell you what buyers in that price range are asking for, and what they won’t pay for.
  • Launch and sales. Pricing, staging, photos, marketing and managing showings and offers through settlement.

Have a lot or a project in mind?

Tell me the address and what you want to build. I’ll follow up personally.

Want the market in your inbox? My Philadelphia Developer’s Report is for people who build and sell new construction in Greater Philly.

Frequently asked questions

How do I know if I can build by right in Philadelphia?

Look up the lot in Atlas to see the zoning district and overlays, then check what that district allows with the City’s Zoning Summary Generator. If your plan fits the district’s use, size and setback rules, you can apply for a zoning and building permit without the Zoning Board. Have an architect who knows the Philadelphia code confirm it before you buy.

How long does a zoning variance take in Philadelphia?

The Zoning Board’s 2026 manual put the wait for a regular hearing at about 180 days as of March 2026, or about 140 days if you pay the accelerated fee. You must appeal within 30 days of L&I’s refusal, and you also need to give notice and meet with the RCO first. My own variance took the better part of a year during COVID.

Does new construction still get the 10-year tax abatement?

Yes. Under the current residential new construction program, the land is fully taxed and the abated share of the building steps down 10% a year for 10 years. The owner or developer must apply to the Office of Property Assessment within 60 days of the building permit being issued.

What is the Development Impact Tax?

It’s a City tax of 1% of construction cost on residential new construction over $15,000. Half is due when the building permit is issued and half before the certificate of final inspection. For new construction, eCLIPSE calculates the cost from a per-square-foot table.

How long does L&I take to review a building permit?

L&I lists 15 business days for new construction of a one- or two-family home and 20 business days for most other projects, plus a day for pre-processing. Accelerated review within 5 business days costs $2,000.

Do I need a stormwater plan for a townhome project?

It depends on how much ground you disturb. Under 5,000 square feet, PWD doesn’t require an ERSA submission. From 5,000 square feet up you need an approved erosion and sediment control plan. Since July 1, 2026, one- and two-family projects under one acre are exempt from post-construction stormwater management, except where watershed rules apply.

What does an RCO do?

A Registered Community Organization represents a neighborhood in the zoning process. If you need a variance or special exception, or your project triggers Civic Design Review, you must notify the Coordinating RCO and attend a public meeting it holds, and the RCO reports back to the Zoning Board or the review committee.

What are new construction homes selling for per square foot in Philadelphia?

From November 1, 2025 through October 31, 2026, new construction homes in Philadelphia County sold at a median of $281 per above-grade square foot, and townhouses and rowhomes at $269, based on information from Bright MLS. That’s a resale value for a finished home with the land, not a build cost. In my experience the hard cost to build runs roughly $150 to $200+ per square foot, before land, soft costs and financing. The range of sold prices by ZIP is wide, from $225 in 19134 to $927 in 19107. Information Deemed Reliable but Not Guaranteed.

Can you help me find land?

Yes. That’s how our team got into new construction. Tell me the product you build, your budget and the neighborhoods you like, and I’ll send you sites, including off-market ones, with the zoning checked.

Sources

Every figure on this page was checked against the source below on November 22, 2026. Rules and fees change, so confirm with the City before you rely on a number, and talk to your own attorney, architect and accountant. This page is general guidance, not legal, tax or financial advice.

How I update this page: I review it every quarter and whenever a fee, tax rate or timeline changes. The date at the top shows the last time I changed it.